EVALUATION & LISTING SERVICESNovember 1, 2011
FEE1
Innovative Products:  
No Applicable Technical Guide  
  • Scope and Evaluation Plan (SEP)
$7,575
  • Technical Guide Preparation
at cost2
  • Data review for New Report
at cost
  • Evaluation Report Preparation
$9,100
Existing Technical Guide  
  • Data review for New Evaluation
at cost
  • New Evaluation
$10,610
  • Re-evaluation of Report
$7,570
  • Minor Technical modification of Report3
$1,920
  • Administrative modification of Report3
$100 - $300
  • Revision to Technical Guide
at cost
   
Standardized Products:  
Evaluation Listing  
  • New Evaluation
$5,615
  • Re-evaluation
$4,105
  • Certified product
$1,625
  • Minor Technical modification of Listing3
$1,210
  • Administrative modification of Listing3
$100 - $300
  • New Evaluation Directive/Preface
at cost
   
Extra Services (if applicable):  
  • Test results from non-recognized lab
$1,080
  • Additional product/item under same CCMC Number
$630
  • Quality control review
$950
  • Additional manufacturing plant/licensee
$630
Notes:
1.  New evaluations and re-evaluations are valid for three years. A 10% discount also applies to fixed fee services, if client has more than 1 evaluation/listing with CCMC. These fees are in Canadian funds, do not include applicable taxes and are subject to change without notice.
2.  The cost of preparing a Technical Guide is dependent on the resources expended by CCMC. New proponents may participate at a reduced cost if their products would be subject to a Technical Guide that is still under development or that was completed within the preceding three years, by paying:
  • 50% of the cost charged to the first proponent, and NRC will refund that amount to the first proponent;
  • or, if there were multiple earlier proponents, the same cost that they were charged, but NRC will not make a refund.
3.  There is no charge for editorial modifications.